Enter the diameter and depth of the form tube, the size of the footing pad if there is one, and the number of footings. The calculator works out the concrete for each footing and for the whole job, adds extra for spillage and rounds up to whole bags.

For a flat patio, walkway or shed slab, use the concrete slab calculator instead, and for posts set straight into the ground, the post hole concrete calculator.

How the footing calculator works

  • Pier = π × (diameter ÷ 2)² × depth, the volume of a round form tube.
  • Pad = width × width × thickness for a square footing under the pier. Leave the pad fields empty if there is none.
  • Bags = (pier + pad) × number of footings, plus the extra percentage, divided by the yield of one bag and rounded up. An 80 lb bag of pre-mixed concrete makes about 0.6 cu ft.

This calculator only estimates concrete. It does not size footings. The diameter, the pad size and how deep the footing goes below the frost line depend on the load, the soil and your local building code, so check with your building department before you dig.

Concrete per pier

Tube diameter36 in deep48 in deep
8 in1.05 cu ft (1.9 bags)1.40 cu ft (2.6 bags)
10 in1.64 cu ft (3.0 bags)2.18 cu ft (4.0 bags)
12 in2.36 cu ft (4.3 bags)3.14 cu ft (5.8 bags)
16 in4.19 cu ft (7.7 bags)5.59 cu ft (10.2 bags)
18 in5.30 cu ft (9.7 bags)7.07 cu ft (13.0 bags)
Bags are 80 lb (0.6 cu ft each) with 10% extra; round the total for all piers up to whole bags.

Concrete per footing pad

Pad sizeVolume
16 × 16 × 8 in1.19 cu ft
20 × 20 × 8 in1.85 cu ft
24 × 24 × 10 in3.33 cu ft
Add the pad to the pier for each footing.

Worked example

A small deck sits on 4 footings, each a 10 in tube 48 in deep on a 20 × 20 × 8 in pad. Each footing holds 2.18 + 1.85 = 4.03 cu ft. Four footings need 16.1 cu ft, or 17.7 cu ft with 10% extra. At 0.6 cu ft per 80 lb bag that is 29.6, so buy 30 bags.

Step by step: estimating concrete for footings

Deck layout with string lines and stakes marking footing locations
Step 1. Lay out the deck and mark where each footing goes; count them.
Post hole dug in the ground with a measuring tape showing depth
Step 2. Dig each hole to the depth your code requires and measure it.
Cardboard form tube standing in a hole on a square concrete pad
Step 3. Set the form tube level and plumb on the pad or the hole bottom.